The deal
Applied Digital (NASDAQ: APLD) said Monday it has entered into an 18-year lease with a tier-one investment-grade hyperscaler for 150 MW of critical IT capacity at Delta Forge 1, its AI Factory campus in Louisiana. The lease carries approximately $5.4 billion in base-term contracted revenue — about $12.7 billion if all renewal options are exercised over a 33-year total term — and the tenant was not named.
With the addition, Applied Digital's total contracted base-term lease revenue exceeds $41 billion, or roughly $100 billion including all renewal options. The portfolio now stands at more than 1.6 GW of contracted critical IT load and 2.2 GW of grid-connected peak load, with about 75% of base-term lease revenue attributable to investment-grade customers, the company said.
Pricing power, in writing
The lease "contains improved commercial terms over our prior leases, including higher pricing," Applied Digital said — and the arithmetic backs the direction of travel. The June Delta Forge 2 lease (210 MW, about $5.2 billion over 15 years) worked out to roughly $1.65 million per MW-year; this deal's announced terms imply about $2.0 million per MW-year. PulseGrid calculated both figures from the companies' announced deal values, durations and capacities.
The structure echoes the company's established financing playbook: first-in equity already funded from the balance sheet and through the $5 billion programmatic equity partnership with Macquarie Asset Management, followed by project financing supported by the long-term lease. CFO Saidal Mohmand said the remaining project finance for Delta Forge 1 and Polaris Forge 3 is expected in the first calendar quarter of 2027, with Delta Forge 2 following in the second quarter. Separately, the company closed a $300 million senior secured bridge facility to support Delta Forge 1 construction. Delivery of the newly leased capacity is expected to begin in the first half of 2028, subject to development milestones, utility arrangements and regulatory approvals.
Credit quality as the new moat
"Securing another large-scale, long-term lease with a tier-one investment-grade hyperscaler reinforces to us the strength of our customer relationships and the quality of our contracted revenue," said Wes Cummins, Applied Digital's chairman and CEO. The emphasis on credit quality is deliberate: with roughly three-quarters of contracted base-term revenue now investment-grade, the company is selling the AI capacity buildout as long-duration infrastructure cash flow rather than speculative colocation.
AI-assisted analysis
Machine-synthesised- Fact
Applied Digital has entered into an 18-year lease agreement with a tier-one investment-grade hyperscaler for 150 MW of critical IT capacity, providing approximately $5.4 billion in base-term contracted revenue, at its Delta Forge 1 campus in Louisiana.
Source: Applied Digital Corporation (investor relations)(opens in a new tab) - Figure
The lease is worth approximately $12.7 billion if all renewal options are exercised over a 33-year total term; Applied Digital's total contracted base-term lease revenue now exceeds $41 billion, or approximately $100 billion with all renewals, with about 75% attributable to investment-grade customers.
Source: Applied Digital Corporation (investor relations)(opens in a new tab) - Fact
The lease contains improved commercial terms over prior leases, including higher pricing, and delivery of the capacity is expected to begin in the first half of calendar 2028, subject to development milestones, utility arrangements and regulatory approvals.
Source: Applied Digital Corporation (investor relations)(opens in a new tab) - Figure
On the announced terms, the lease prices at roughly $2.0 million per MW-year, versus about $1.65 million per MW-year on Applied Digital's June Delta Forge 2 lease (210 MW, about $5.2 billion over 15 years) — an indication that AI capacity pricing is rising.
Source: Applied Digital Corporation (investor relations)(opens in a new tab)
Synthesised by PulseGrid's editorial AI from the sourced claims in this article and reviewed by PulseGrid AI Desk. How we use AI.
Partner content · paid placement
Sponsored tile inventory: Q1 2027
Native tiles in the in-feed carousel and the article block, sold only with the visible Sponsored / Partner Content label. Slot sizes, positions and advertiser terms are published on the advertise page. No newsroom byline is ever attached to partner copy.
For the wider market, the deal is a live price point for AI capacity. Delivery timelines keep slipping across the industry — power queues, interconnection studies and equipment lead times dominate the discourse — yet the capacity that does get contracted is repricing upward and concentrating in credit-quality tenants. That combination is a running theme of the 2026 buildout: scarcity economics arriving alongside a flight to quality. Shares of Applied Digital rose about 13% on Monday morning following the announcement.
What to watch
Three markers will show whether this pricing holds: whether the project finance for Delta Forge 1, Delta Forge 2 and Polaris Forge 3 closes on the guided Q1–Q2 2027 schedule; whether the unnamed hyperscaler's renewal options convert the $5.4 billion base term toward the $12.7 billion ceiling; and whether subsequent leases print above the ~$2.0 million per MW-year implied here — the clearest public gauge of where AI capacity prices are heading.
Bottom line
The AI capacity market is bifurcating on credit quality and price. Applied Digital's fourth-quarter marquee lease shows hyperscalers still signing decade-and-a-half commitments — and paying more per megawatt than they did five months ago.