Second campus reaches Ready for Service

Applied Digital (NASDAQ: APLD) has completed base-build commissioning for the first 75 MW of its initial 150 MW data-center building at Polaris Forge 2 in Harwood, North Dakota, and achieved Ready for Service on the first 25 MW data hall — on schedule, the company announced on November 24.

It is the first Ready for Service achievement at Applied Digital's second AI Factory campus, following 250 MW of operational critical IT load delivered at Polaris Forge 1 in Ellendale, North Dakota. With the base-build infrastructure for the full 75 MW phase tested and commissioned, the remaining 50 MW can advance through fit-out and customer delivery.

The delivery model, and what is leased

The building is fully leased as part of the customer's 200 MW long-term lease at Polaris Forge 2, contributing to a portfolio of more than $41 billion in contracted base-term lease revenue, according to the company. Each 150 MW building at the campus is commissioned in two 75 MW phases, with three 25 MW data halls tested and commissioned together during each phase — a modular cadence that is the operational heart of the "repeatable execution" claim.

"AI infrastructure demand is not theoretical for us. It's backed by long-term customer commitments, and our focus is on delivering against them," said Wes Cummins, chairman and CEO of Applied Digital. "With our second campus now reaching Ready for Service on schedule, we're demonstrating that our execution model is repeatable." Cummins argued that "the ability to consistently turn contracted demand into delivered AI capacity is what will define the leaders in this industry."

Why one milestone matters

The AI data-center sector is being priced on execution risk: announcements are abundant, delivered megawatts are not. A second campus hitting its Ready-for-Service date converts a first-project story into something closer to a delivery track record — the asset class's most watched qualitative metric.

AI-assisted analysis

Machine-synthesised

Synthesised by PulseGrid's editorial AI from the sourced claims in this article and reviewed by PulseGrid AI Desk. How we use AI.

Partner content · paid placement

The caveat is the source. This is an Applied Digital press release: the megawatt figures, the lease portfolio and the schedule claims are the company's own, and the customer behind the 200 MW lease is unnamed. Still, the base-build commissioning sequence (75 MW phases, 25 MW halls) is concrete, checkable operational detail of the kind the delivery-bottleneck debate has lacked.

What to watch

The remaining 50 MW of the first PF2 phase moving through fit-out to customer delivery — the next cadence check on the two-75-MW-phase model.

Whether the >$41B contracted portfolio keeps growing at the ~$2.0M/MW/yr pricing the recent Delta Forge lease signaled.

Grid and power sequencing at Harwood as the campus scales past its first building.

Bottom line

Applied Digital's second campus is now delivering megawatts on schedule, which is the single strongest thing a data-center developer can say in this market. Company-sourced figures deserve the attribution they carry — but the direction is unambiguous: contracted demand is turning into commissioned capacity, one 25 MW hall at a time.